Mailiilii Road Emergency Repair project.

“The contractor is currently constructing the head-wall for the road and drain. This should be poured by the middle of next week. The head-wall needs to be cure for a minimum of 7 days after the pour. The road reconstruction can begin after the curing period and should take about a week and a half before the road can be opened.” – Board of Water Supply