For Immediate Release: March 28, 2014
14-0096
OAHU LANE CLOSURES FOR THE WEEK OF MARCH 29 – APRIL 4
PLEASE NOTE: Lane closure schedules may change at any time without further notice.
All projects are weather permitting.
— H-1 FREEWAY —
PEARL CITY (WEEKEND/NIGHT WORK)
Three right lane closures on the H-1 Freeway in the eastbound direction between the H-1/H-2 Merge and the Pearl Ridge/Waimalu Off-Ramp (Exit 10) on Monday, March 31, through Friday morning, April 4, from 6 p.m. to 4:30 a.m., for viaduct deck repairs.
For more information, please visit the project website at www.pmcontraflow.com or call the project hotline at (808) 945-1144.
WAIMALU TO PEARL CITY (NIGHT WORK)
Center lanes will be closed on the H-1 Freeway in the westbound direction between the Waipahu Off-Ramp (Exit 8B) to the H-1/H-2 Split on Monday night, March 31, through Friday morning, April 4, from 7:30 p.m. to 4:30 a.m., for repaving.
For more information, please visit the project website at www.pmcontraflow.com or call the project hotline at (808) 945-1144.
HONOLULU (NIGHT/WEEKEND WORK)
Two lane closures on the H-1 Freeway in both directions between Ward Avenue Overpass and Likelike Highway on Monday, March 31, through Friday, April 4, from 8 p.m. to 5 a.m., for the H-1 Rehabilitation Project.
For more information, please visit the project website at www.H1Rehab.com or call the project hotline at (808) 735-7465.
HONOLULU (NIGHT WORK)
Lane closures on the H-1 Freeway in the westbound direction between Kokohead Avenue Overpass and the King Street Off-Ramp (Exit 25A) on Monday, March 31, through Friday, April 4, from 9 p.m. to 4 a.m., nightly, for sign repairs.
WAIMALU TO WAIPAHU (NIGHT WORK)
Two left lanes closed on the H-1 Freeway in the westbound direction between the Pearl City/Waimalu Off-Ramp (Exit 10) and the Waikele/Waipahu Off-Ramp (Exit 7) on Monday, March 31, through Friday morning, April 4, from 10:30 p.m. to 4:30 a.m., for Pearl City Viaduct deck repairs.
For more information, please visit the project website at www.pmcontraflow.com or call the project hotline at (808) 945-1144.
SALT LAKE TO HONOLULU INTERNATIONAL AIRPORT (NIGHT WORK)
Two right lane closures on the H-1 Freeway in the eastbound direction between the Radford Drive Overpass and the Airport Off-Ramp (Exit 16) on Monday, March 31, through Friday, April 4, from 8 p.m. to 4 a.m., nightly, for overhead sign work.
EWA (NIGHT WORK)
Lane closure on the H-1 Freeway in the eastbound direction between Kapolei/Ewa Off-Ramp (Exit 3) and Kunia/Waipahu/Ewa Off-Ramp (Exit 5) on Monday, March 31, through Friday, April 4, from 8 p.m. to 3:30 a.m., for sign work.
— H-3 FREEWAY —
HALAWA
Lane closures on the H-3 Freeway in the Kaneohe-bound direction between the Halawa Interchange and the Likelike Highway on Monday, March 31, through Friday, April 4, from 9 a.m. to 3 p.m., daily, for marking installations.
— FARRINGTON HIGHWAY —
MAKAHA
Single lane closure on Farrington Highway in the eastbound direction between Jade Street and Makaha Valley Road on Monday, March 31, through Friday, April 4, from 8:30 a.m. to 3 p.m., daily, for drainage maintenance. Traffic will be contraflowed using the remaining open lane.
During these hours, the east entrance to Lahilahi Street may also be closed as needed. Access will still be available at the west entrance to Lahilahi Street.
EWA (WEEKEND/NIGHT WORK)
24-hour lane closures on Farrington Highway in both directions between Kualakai Parkway and Fort Weaver Road on Sunday, March 30, through Friday, April 4, for the rail project.
WAIPAHU
Lane closures on Farrington Highway in both directions between Old Fort Weaver Road and Mokuola Street on Monday, March 31, through Friday, April 4, from 7 p.m. to 6 a.m., for the rail project.
###